Work substantially complete on Beaver Street and Butler Avenue

Work to implement a pilot project installing separated bike lanes on Beaver Street and Butler Avenue is substantially complete for installation of the curbs and candlesticks as designed.  The City is working to modify and re-installing candlesticks that have been hit or damaged by vehicular traffic. 

Originally the pilot project, Phase I and II, was scheduled for completion by the end of 2021.  The contractor was able to receive materials and successfully install the curbs and candlesticks ahead of schedule.  November 19, 2021 is the date of substantial completion.  

Work continues on Butler Avenue to implement the separated bike lanes pilot project

Work continues to implement a pilot project installing separated bike lanes on Beaver Street and Butler Avenue. The contractor has completed the installation of a concrete curb and delineators to physically separate bicyclists from vehicles on Beaver Street.

Work to install similar barriers on Butler Avenue will begin on Monday, November 15, 2021 and end on November 26, 2021.  The project limits are Butler Avenue, from Milton Road to Sawmill Road.