Beaver Street closure to resume February 26

FLAGSTAFF — Starting Feb. 26, 2018, Beaver Street will close from Columbus Avenue to Birch Avenue (see attached map). This closure will allow construction of the final utility and roadway improvements to resume after a winter hiatus.

The north three side streets (Sullivan Avenue, Hunt Avenue and Fine Avenue) will be open to accommodate traffic flow across Beaver Street, and to allow business and resident access on Beaver Street for northern portion of the project. Southbound traffic will be allowed on Beaver Street between Sullivan Avenue and Fine Avenue. A detour will re-route traffic from Beaver Street to Humphreys Street starting at Columbus Avenue and then back onto Beaver Street at the south end of the project. NAIPTA bus route #2 will continue operating temporarily on Humphreys Street during this closure.

Construction is expected to be complete on both Beaver and Dale in the summer of 2018.

For more information contact City of Flagstaff Project Manager, Eli Reisner at (928) 213-2679, ereisner@flagstaffaz.gov.